Construction of new 33/13.8kV S/S 7822
MEECO Scope of Works:
Providing complete engineering & design services.
Electrical:
Design calculations for Grounding, Indoor and Outdoor lighting, shielding, equipment sizing, Layout drawings preparation, Cable routing, AC & DC package, Vendor document review and preparation of Bill of Quantities is under the scope .
Protection:
Preparation of protection & metering logic diagrams. Preparation of detail design, cable schedule, SCADA points list, CT/VT sizing and relay settings.
Civil:
Design of substation building with cable trench, power transformer, foundation site development plan, boundary fence & etc.
Mechanical:
HVAC design for complete substation with ventilation for transformer area. Ventilation calculation for power transformers.